In this section:
Progress Gallery
In the first few weeks of May 2010 the steel frame for Tresham's new Corby campus has begun to rise from the ground.

Tarmac has been laid for the carpark
In April 2010 BAM Construction have continued to develop site in Oakley Road, Corby and have begun to lay the foundations for the new building as these aerial shots show.
Aerial photographs courtesy of Chris Mills, Still Imaging.


Once the foundations were laid, retaining walls were built

Demolition of the former Corby Community College buildings began in November 2009 and BAM Construction are on schedule for the building project to be ready for students in September 2011.